Owner need to contact (IZI) Hoa Cam industrial zone joint stock company investment Before who decide to take out a permit investment, inorder to reach conditions of investment as follows:
- Research generality about feature, Hoa Cam industrial zone's situation taken.
- Inquiring necessary information about law and policies for project.
- Inquiring profession object invested in industrial zone, policy favour when invest in Hoa Cam industrial zone.
- Survey about national service infrastructure, utility, land’s rate, public service, comforts in industrial zone.
- Select and deal about lot of ground which is suitable position and area.
Present invest demand by subscription invested form deliver over at Room invested- IZI to register investment.
1. WRITTEN IS INVESMENT
a. Process resolved
- After research investment environment at IZI if achieved the necessity, Owner deliver over investment subscription file to register at Room invested- IZI.
- Condition to consider acquiescence investment : Project there is business produced matches industrial zone's planning and assure criteria about sanitation. If conditions fiability project invest in industrial zone, IZI'll report by text come to Owner concerning acquiescence investment.
- When receive report concerning acquiescence investment, the investment Owner deliver over in advance with value like have already been pledged in subscription invested and send certificate bestowal subscription file invested and note of authority (if any) at room invested- IZI.
b. Investment subscription file contents
- Subscribe to investment (according form No. 01/ĐKĐT/IZI-ĐT owing to IZI is gradated).
- Amount: 01 set.
c. For period of time resolvedc.
- 05 days as of day IZI have enough of validity file.
2. CERTIFICATE BESTOWAL IS INVESTED
a. Process resolved
- IZI will united with Da Nang industrial zones management committee and Export processing zone certificate investment for Owner.
b. Investment Certificate subscription file contents
- Certificate bestowal subscription invest by appendix sampled I-1a,b that IZI bestowal.
- Note of authority in case have delegation of authority.
- Amount: 02 sets.
c. Period of time is resolved
- 15 days as of day IZI is recipient enough valid file.
3. DRAW UP MINUTES TO AGREE LAND SUBTENANCY
- Owner carried out draw up minutes of land sustenance accordance to reach an agreement with IZI. Later IZI will provide mappings about: position diagram, lot size, heart remains, way building restriction line corresponds.
4. PLANNING CERTIFICATION BESTOWAL
a. Process resolved
- Owner deliver over planning certification bestowal subscription file at room invested.
- IZI will united with Da Nang industrial zone management committee and export processing zone for planning certification bestowal for Owner.
b. Planning certification bestowal subscription file contents
- Tender planning certification bestowal according to denominator No. 02/CCQH/IZI-ĐT owing to IZI is gradated.
- Plan mapping employs land (copy).
- Land subtenancy memorandum.
- Number of file: 02 sets.
c. For period of time resolved
- 02 days, as of day IZI sink enough of validity file.
5. AGREEMENT CONSTRUCTION FILE
a. Resolve process
- Owner deliver over construction accordance file at investment room - IZI.
- IZI will aggregate with industrial zone management committee and export – processing zone for approving construction accordance file.
- IZI will approve agreement of infrastructure connecting.
b. File contents agrees construction
- Missive tender building architecture solution and total design plan accordance According to form No. 03/TTTK/IZI-ĐT owing to IZI is gradated.
- Infrastructure connecting accordance proposal missive.
- Mappings designs plan Sum include: constructions items master plan mapping, plan Sum to rake in and drainage, water supply plan Sum, voltaic level, intestine traffic.
- Architectural design mapping includes: gateway plan mapping, wall lateral face profile, standing face, hedge of constructions items.
- Infrastructure connect mappings.
- Report of environmental impacting or subscription measure reach environment criteria according to current ordinance.
- Amount: 06 sets are original. Owner will receive again 02 sets after get approving.
c. Time-limit resolved
- 03 days, as of day IZI revives enough of validity file.
6. COVENANT LAND UNDERTENANCY CONTRACT
- Covenant land subtenancy contract at business department- IZI and deliver over the rent at counting house- IZI executive Owner.
7. BUILDING INVESTMENT EXECUTIVE
- After there is minute-book in official lot transferred, Owner carried out building construction that is pursuant treaty design.
- The investor notify to set construction first 05 days, IZI supervise locate buildings close to red line of landmark, construction landmark, ground elevation is assumed.
8. BUILDING FINISHED WORK LEGITIMATING
a. Investment executive
- After finishing the building, Owner need to relate with industrial zone management committee and Danang exporting processing finishing building in order to carry out building finished procedure to show in buildings used.
b. Homologative building file contents
- Land subtenancy contract owing to owner is agreed with IZI.
- Proposal text cognizance of finishing building.
- Construction contract with unit has legal person’s capacity.
- Building acceptation inspection minute-book according to just government regulation about building quality management.
- Acceptation inspection minute-book about environment criteria, criteria protect against detonating combustion.
- Record drawings owing to two party A, B and technician signing.
c. Time-limit is resolved:
- Enough of validity file 07 days since receiving.
Note
In the course of resolving file and carries out project, Owner will continuously guide to IZI continue take out subscription confirmation note of environment criteria at resources Bureau and environment, implement fire protection procedure extinguish the fire, Prevent burst according to regulations, implement environment protective measure in the course of construction and produce according to subscription contents reach environment criteria.