- Location: Hoa Tho Tay ward, Cam Le district, Danang city, Vietnam.
- Total investment capital: VND 79,394 million.
- Implementation Plan in 2010:
- Implement the clearance compensation, planning, setting up investment projects, detailed designing and constructing part of levelling item. - Investment value of the 2010 plan: VND 8,704 million.
Read more...
- Location: No. 1 street, Hoa Cam IZ (Phase 2)
- Total investment capital: VND 36,579 million.
- Implementation Plan in 2010:
- In 2010 to build 01 wastewater treatment plant with capacity of 2000m3 per day. - Investment value of the 2010 plan : VND18,916 million.
Read more...
- Location: Hoa Tho Tay ward, Cam Le district, Danang city, Vietnam.
- Total investment capital: VND 361,210 million.
- Implementation Plan in 2010:
- Implement the clearance compensation, planning, setting up investment projects, detailed designing and constructing part of levelling item to serve the construction of wastewater treatment plant. - Investment value of the 2010 plan: VND14,531 million.
Read more...
- Location: No. 7 street, Hoa Cam IZ (Phase 2).
- Total investment capital: VND 12,206 million.
- Implementation Plan in 2010:
- Recruiting for design team, setting up investment projects, detailed designing and implementing foundation and capital construction of the main building. - Investment value of the 2010 plan: VND 7,262 million.
Read more...
- Location: Hoa Cam IZ (Phase 2).
- Total investment capital: VND 18,439 million.
- Implementation Plan in 2010: in 2010 completed the establishment of investment projects and basic design.
Read more...
|
|
|
|